Skip to main content

Blue Springs High School Concession Stand Floor Coating

Project Summary

Blue Springs High School was undergoing significant renovations to their existing building and one of the items included their cafeteria kitchen. Therefore, the school decided to temporarily move their kitchen into their largest concession stand associated with the sports fields on the South end of their campus. With the equipment and mechanical upgrades needed to efficiently prepare and serve lunch to the hundreds of high schoolers was the need to redcoat the floor to ensure the space was food safe and met all local regulations and requirements. Therefore the school contracted Major Painting to install a high-performance floor coating system to install a seamless flooring system that would allow for easy cleanup and employee and student safety.

Project Highlights

  • Location: Blue Springs, MO

  • Building Type: Commercial

  • Client Type: Local School District Facilities Department

  • Project Duration: 4 Days

Project Scope

  • Day 1: Remove the existing coating and grind the complete floor achieving a profile for the new coating to properly adhere to
  • Day 2: Vacuum floor, prep space, and apply (1) coat of PPG Amerlock 600 Epoxy
  • Day 3: Apply (1) coat of PPG PSX 700 polysiloxane with NonSlip Additive to the complete floor
  • Day 4: Install Masterseal SL1 caulking to the expansion joints and de-prep the space

Color Scheme

Packaged Pearl Gray

Products Used

Base/ Primer Coat: PPG Amerlock 2,
Finish Coat: PPG PSX700 w/ NonSlip Additive

Project Details

Ready to Start Your Next Commercial Project?

We would love to chat with you in more detail about your upcoming commercial painting, remodel, or carpentry project. 

Contact our team of professional commercial painters and carpenters today for a complimentary quote!

Content Reviewed by Chase DeRousse